Downriver disc golf course redesign
1. Moving 18 baskets: 20 bags of concrete-2.50$ per bag plus equipment rental 25-50$(1 day + gas ) total cost and work time= 85-125$ two days ( 4-6 workers)
2. Moving, building and grading teepads: 10 yards 5/8 minus=150$, replacing damaged or worn out fly mats 1000$ equipment rental 50$. Total cost and work time=1200-1400$ 2 workers and two hours per teepad.
3. Installing and repairing teesigns: 10 bags of concrete, hardware 15$ total work time and cost= 40-50$ 1hour per sign off site 1 day 2-4 workers on site ( not included is measuring, mapping and printing out teesigns)
4. Installing 14 benches: 30 bags of concrete, other materials to be donated total cost and work time 75-100$ and 1 man hour on site per bench ( not including off site assembly of benches)
5. Completing tourney central and kiosk: repairing old table, installing benches, painting kiosk and building/installing plexiglass cover. 75-100$ 4-6 man hours ( not included is making signage for kiosk and donation box)
6. Other work to include: erosion control on all hillsides( that are in the areas of play) ;this will include stairs, planting and retaining walls, beautification of over used areas; this includes pathways and plantings, and protection of existing plantlife. Total cost and work time: 500-1000$ (incremental) and unending man hours
Total project estimate 2500$-3000$
note: all existing teepads, teesigns and benches will be reused if possible much of the materials ( lumber, plants, paint etc..will be donated by local players and companies)
|
 |
|
|
|
|
|
|