Work needed to be accomplished on the 8th.

Hopefully the holes will already be augured out for us.

12 4"x4" post will be set for tee signs
14 sleeves will be set for baskets
12 front of the tee kick boards to be set near the tee signs

In addition two holes will need some fairly minor brush clearing in order to create a fairway. Think ivy and black berry bushes and a few small trees.

Chores, hauling bags of concrete to each hole. Lugging buckets of water to use in mixing. Setting the sleeve so the basket will be 100% plumb when installed.

There will most likely be a couple follow up weekends also when we will actually place the baskets, attach the tee signs, etc.